Doubling of Palanpur-Samakhiyali line (248 RKM):

Doubling of Palanpur–Samakhiali project line (248 route km) was successfully completed & commissioned by 24th February 2023 as per certificate issued by Commissioner of Railway Safety (CRS)/Mumbai.

Railway Electrification of Palanpur-Samakhiyali-Gandhidham (301 RKM):
  • RE works on Palanpur to Samakhiali project line (248 route km) was fully commissioned by 24th March’2023 as per certificate issued by PCEE/W.Rly.
  • RE works on Samakhiali to Gandhidham section (UP line/53 RKM) fully completed & commissioned by 8th May’2023 as per certificate issued by PCEE/W.Rly.
SNoDescription
1 Approval for doubling of broad gauge line between Palanpur-Samakhiali section was announced in the Railway Budget of 2013-14 and also approved by Cabinet Committee on Economic Affairs in 2013
2 Documents for Notice Inviting Tender (NIT) for selection of Scheduled Banks for availing Rupee Term Loan of Rs.1000 crores :
3 2(i) The rationale for rating by ICRA Limited
4 2(ii) The Detailed Project Report (DPR) prepared by RVNL
5 2(ii)(a) The Detailed Project Report(DPR) prepared by RVNL
6 2(ii)(b) The DPR prepared by RVNL - General Services Electrical works
7 2(ii)(c) The DPR prepared by RVNL - Annexures
8 2(ii)(d) The DPR prepared by RVNL - Project Estimate-II
9 2(ii)(e) The DPR prepared by RVNL - details of Bridges, LC, etc.
10 2(ii)(f) The DPR prepared by RVNL - Revised Estimate
11 2(ii)(g) The DPR prepared by RVNL - Feasibility report for Electrification
12 2(ii)(h) The DPR prepared by RVNL - Bill of Quantities for RE
13 2(ii)(i) The DPR prepared by RVNL - MOD for RE works estimate
14 2(ii)(j) The DPR prepared by RVNL - Detailed Estimate for electrification
15 2(ii)(k) The DPR prepared by RVNL - Letter for fund requirement
16 2(iii) Bankability Study report prepared by M/s. Feedback Ventures
17 2(vi)(a) Balance Sheet of KRCL for FY 2017
18 2(vi)(b) Balance Sheet of KRCL for FY 2018
19 2(vi)(c) Balance Sheet of KRCL for FY 2019
20 Construction agreement of G.C. dated 6th October 2005
21 O & M agreement between KRC & Western Railway
22 Concession Agreement with Ministry of Railways